Things at The Carriage House are really moving fast!  The slab was poured early Monday and lots more work done on our stone bridge and parking lot.

This picture is the barn concrete slab.  The workers are preparing it for the steel erection, as well as, smoothing it out for eventual staining.  The steel will be delivered the middle of next week after the concrete is adequately cured.  Then The Carriage House will start to rise!  Excited!

This is the stone bridge from previous pictures.  One hundred loads of fill dirt were delivered on Monday to level out the bridge driveway and parking lot.

Can't believe how big these concrete pumper trucks are!  They started arriving at 3am Monday morning.  The weather was perfect for concrete work according to our contractor.